Technical issues on the German train programme have led Alstom to revise its production plans and strengthen verification before approval.

Illustrative photograph · ThisIsEngineering

In its half-year report, Alstom says the Coradia Max platform requires engineering changes and a strategy for modifying trains already built. It has reinforced the test programme as work towards authorisation and passenger service continues.

The revised schedule affects production in the current financial year and the approval timetable across six projects. Teams planning the modifications therefore have to account for units already assembled as well as those still moving through production.

For configuration control, these are separate questions: which trains need the change, which drawing or software revision applies to each unit, and which test demonstrates that the new configuration meets its requirements?